It is impossible to predict the outcome of
litigation. And the lack of predictability can make it difficult
to ascertain the risks of litigation. Not only do the parties
disagree, but the judges also disagree on significant issues.
Two recent Court of Appeals cases highlight the uncertainty that
is inherit in construction litigation, both before trial and after
trial.
In Park Rise HOA v. Resource Construction Co., decided
June 15, 2006, Park Rise Homeowners Association, Inc. (the “HOA”)
brought construction-defects claims against both the developer
of the community and the general contractor. Although the HOA
settled with the developer, the jury still had the task of apportioning
fault for its damages between construction problems (which were
the responsibility of general contractor) and design defects (which
were the responsibility of the developer).
The trial court, relying on a prior Court of Appeals decision,
concluded that the HOA had not presented sufficient evidence to
allow the jury to apportion damages among construction and design
defects. Because of this, the trial court entered a directed verdict
in favor of the general contractor. At that point, the general
contractor had won, based on a ruling interpreting prior Court
of Appeals precedent. But the Court of Appeals reversed the trial
court. According to the Court of Appeals, the HOA had presented
sufficient evidence that the defects complained of for at least
three of its 18 categories of damages were construction errors,
not design problems. Thus, the Court of Appeals sent the case
back (all 18 categories) to the trial court to be tried again
to a second jury.
The Park Rise HOA decision shows how dramatically judges’
opinions on key issues can vary. In addition to showing how judges’
interpretations of the law can differ, Belfor USA Group, Inc.
v. Rocky Mountain Caulking and Waterproofing, LLC, decided
August 9, 2006, shows the unpredictable nature of a jury verdict.
Belfor had hired Rocky Mountain to install caulking and waterproof
coatings on 161 exterior decks of an apartment complex for a lump
sum of $184,831. Rocky Mountain partially completed the work,
and Belfor paid Rocky Mountain only $65,380. The parties then
went to court, both alleging that the other had breached the contract.
Rocky Mountain indicated throughout the preliminary stages of
the lawsuit that it was seeking only $12,582.90 for unpaid work
performed. Rocky Mountain’s mechanics’ lien was for
$12,582.90. In the Trial Management Order, Rocky Mountain identified
that it was seeking $12,582.90. And Rocky Mountain’s principal
testified at trial that only four invoices totaling $12,582.90
remained unpaid. Thus, Belfor and the trial court apparently presumed
that Rocky Mountain was only seeking $12,582.90.
At trial, Rocky Mountain put on evidence that it was not allowed
to perform $106,868.10 in contract work. But the trial court directed
the jury to ignore testimony related to lost profits, because
Rocky Mountain had not made a claim for lost profits. Despite
the trial court’s instruction to the jury, after trial,
the jury awarded damages to Rocky Mountain for $106,868.10, the
exact amount in contract value that Rocky Mountain’s principal
testified his company was not allowed to perform.
The trial court then reduced the jury award to the $12,582.90
that Rocky Mountain had been claiming since the beginning of the
lawsuit. The trial court did this primarily because of Rocky Mountain’s
continued representation throughout the various states of the
case that is claim was for $12,582.90. But on appeal, the Court
of Appeals reversed the trial court, and reinstated the jury award
of $106,868.10, plus pre- and post- judgment interest. The Court
of Appeals appears to suggest in its opinion that had the trial
court chosen a different vehicle or rule by which to reduce the
jury award, then it would not have been reversed.
Both Park Rise HOA and Belfor have legal implications
beyond what is mentioned above. But still, they both highlight
the unpredictable nature of litigation. This intangible, yet real,
factor should be considered when considering settling a dispute.
Timothy
W. Gordon, Esq. is an associate in Holland & Hart LLP's Construction and Real Estate Litigation Group. |