Insurance companies are not jumping at the chance to pay construction-defects
claims. There is an ongoing struggle over insurance coverage
for defective construction, and the courts continue to draw the
boundaries of what the policies cover and what they do not.
One general category of risk that insurance companies often
point to as not being covered is “business risk.” The business
risk doctrine is the idea that insurance is not meant to cover
risks within the policy holder’s control. But general doctrines
do not determine coverage issues. Instead, the actual policy
language controls. On April 22, 2004, a division of the Colorado Court of Appeals
held that a contractor’s insurance policy did not cover
economic damage caused by the contractor’s partially-completed
defective work. McGowan v. State Farm Fire and Casualty Co.,
2004 WL 856511 (Colo. App. April 22, 2004). The McGowans contracted
with Eagle Summit Construction Co., Inc. (“Eagle Summit”)
to build a 3,200-square-foot house for them. Dissatisfied with
the quality of Eagle Summit’s work, the McGowan’s
terminated Eagle Summit after rough framing was complete, and
hired another contractor to finish the project.
The McGowan’s sued Eagle Summit, seeking to recover
the costs for competing their home per the original plans.
And the
trial court awarded the McGowans approximately $400,000.00 damages
for the costs of repairs to correct construction errors and to
complete the house according to contract specifications.
State Farm Fire and Casualty Co. (“State “Farm”)
had issued contractor’s policies to Eagle Summit for the
period during the construction of the McGowan’s home. The
policies covered sums that Eagle Summit was legally obligated
to pay as damages because of damage to property caused by an “occurrence” during
the policy period. After receiving their judgment, the McGowans
attempted to collect the judgment against State Farm. But the
trial court determined that State Farm did not have to pay the
judgment because of the faulty workmanship exclusion (one of
the key business-risk exclusions) in the CGL policy. The Court
of Appeals agreed.
The faulty workmanship exclusion is often found at Exclusion
j(6) of many CGL policies. The faulty workmanship exclusion excludes
coverage for property damage to “that particular part of
any property that must be restored, repaired or replaced because
your work was incorrectly performed on it. . . . ”
This exclusion precludes coverage for the costs to repair
or replace defective work discovered while the insured
is still
performing its work. The faulty workmanship exclusion includes
an exception for damage covered by the products-completed operations
hazard. That exception “includes all . . . property damage
arising out of your product or your work except products that
are still in your physical possession or work that has not yet
been completed or abandoned. . . . ”
The Court of Appeals held that the faulty workmanship exclusion
clearly applied to the McGowans’ claim/judgment against
Eagle Summit. According to the Court:
The McGowans were . . . seeking to recover the expenditures
they were required to make to repair the damage caused
by Eagle Summit’s
faulty and incomplete work. Thus, their claims fall squarely
within [the] Exclusion . . . , as the trial court properly
concluded.
The Court also held that the “products-completed operations
hazard” exception to the faulty workmanship exclusion was
inapplicable. By definition, products-completed operations hazard
exception applies only to work that is “deemed completed.” Eagle
Summit was terminated after rough framing. Thus, its work was
not completed. In fact, the McGowans sued Eagle Summit for the
cost to complete their home.
While not necessarily a ground-breaking decision, McGowan does raise a couple of issues worth noting. First, plaintiffs’ lawyers
will have to keep this decision in mind when deciding who to
sue, and for what causes of action.
For instance, the result would not have necessarily be the
same if the McGowans had received judgments directly against
Eagle
Summit’s subcontractors for negligence. The McGowans could
have brought negligence actions directly against Eagle Summit’s
subcontractors who had finished their work. And the subcontractors’ insurance
carriers would not necessarily be able to rely on the faulty
workmanship exclusion, or the property-being-worked-on exclusion
typically found at exclusion j(5) of many CGL policies. If the
subcontractors’ work was completed, then the products-completed
operations hazard exception would likely apply, thus allowing
coverage.
Second, McGowan illustrates the importance of requiring performance
bonds, and the results if you don’t. An owner considering terminating a contractor
(or contractor considering terminating a sub) for faulty workmanship should
also keep the lesson learned from McGowan in mind. Termination-for-cause clauses
typically allow the owner to recover from the terminated contractor certain
cost overruns. But if the terminated contractor is judgment proof, the owner
should not have any delusions, after McGowan, of recovering against the terminated
contractor’s insurance carrier. As the Court of Appeals noted, CGL “policies
. . . are not intended to be the equivalent of performance bonds.”
Timothy
W. Gordon, Esq. is an associate in Holland & Hart LLP's Construction and Real Estate Litigation Group. |