TABLE OF CONTENTS
1. INTRODUCTION...
- Types Of Risks To Which Parties To A Construction Contract
Can Be Exposed, And Which Can Be Managed, Allocated And Transferred
- Methods Of Management, Allocation And Transfer Of Construction
Project Risks
2. PROCEDURAL RISK MANAGEMENT, ALLOCATION AND TRANSFER CLAUSES..
- Choice Of Law Clauses
- Forum Selection Clauses
- Notice Clauses
- Contractual Statutes of Limitation
- Mediation Clauses
- Arbitration Clauses
- Waiver Of Trial By Jury
- No Discovery Clauses
- Summary Of Procedural Clauses
3. DAMAGE LIMITATION CLAUSES..
- Limitations On Types Of Damages For Which A Party Can Be
Liable
- Limitations On Recovery Of Incidental And Consequential Damages
- Liquidated Damage Clause
- Punitive Damages
- Specific Occurrences: No Damage For Delay
- Limitations On Amounts Of Damages For Which A Party Can Be
Held Liable
- Attorney Fees And Costs
- Exculpatory Clauses: No Liability For Negligence
- Indemnity Clauses
- Mechanics Lien
4. ALLOCATION OF COST OF COVERING RISKS..
- Insurance Coverage
- Site Investigation
- Indemnification
- Performance Bonds
5. SHOULD YOU USE THE RISK ALLOCATION AND TRANSFER CLAUSES?
- Are The Clauses Valid And Enforceable?
- Even If The Clauses Are Valid And Enforceable, Do You Want
To Use The Clauses?
6. CONCLUSION
1. INTRODUCTION
Every construction project, indeed, every portion of a construction project,
almost by definition carries with it numerous risks to the parties to the contract. In
sum, construction projects are inherently risky to all parties. This
article deals with the types of clauses that might be used by the parties in
their contracts to manage, allocate and transfer among the parties to the contract
the risks involved in the construction activity. Of course, usually the
parties to a contract cannot allocate or transfer risks of liability/responsibility
insofar as the rights of the third parties.
Most peoples initial reaction to management, allocation and transfers
of risks is lets transfer every risk I have. A
natural response. Nevertheless, upon more considered deliberation, most
people in the construction industry recognize that there is an allocation of
risks that properly recognizes the role of each party to the construction project
and the ability of each party to bear the risks. Hence, the most important
section of this article may be the last section: should you and can you
transfer risks.
Please note that the sample clauses hereafter are not drafted for insertion
into contracts. Rather, they are drafted to provide basic ideas as to the
types of clauses that can be considered. One who decides to use such types
of clauses must draft the clauses to meet the particular facts and circumstances
presented, only after fully considering the validity and desirability of the
clause.
a. Types Of Risks To Which Parties To A Construction Contract Can Be Exposed,
And Which Can Be Managed, Allocated And Transferred
As indicated above, there are numerous risks inherent in a construction project,
but not all risks are risks of all parties involved in the project. More
important, however, is what risks should be the risks of which parties. For
example, being unable to obtain financing for a project normally is a risk
for the owner/developer. Should financing be a risk of the subcontractor? Ever? In
what circumstances?
This article is about management, allocation and transfer of construction
project risks through contract clauses. Of course, many risks have been
managed by the legislature. For example, the contractor, subcontractor,
supplier and labor have always had a risk of not being paid, because of one or
more risks occurring. The legislature has minimized that risk and
shifted much of the risk to the owner, by providing for mechanics liens
(except as to certain residential projects). Thus, the owner may urge that
it should not be responsible to unpaid subcontractors; however, the legislature
generally has transferred at least a portion of the risk of the contractor not
paying its subcontractors to the owners. However, can the parties override
the legislative grant of mechanics liens? See C.R.S. § 38-22-119.
i. Examples of risks on a construction project
(1) Owner risks
(a) Inability to obtain financing
(b) Default of the financier
(c) Unforeseen conditions
(d) Defective design
(e) Defective construction
(f) Delayed construction
(g) Cost overrun
(h) Destruction of project by the elements (fire, wind, flood, etc.)
(i) Construction site injuries to construction personnel and third parties
(2) Architect risks
(a) Misunderstanding owners intent for the project
(b) Defective design
(c) Underestimating cost
(d) Negligent inspection/observation
(e) Unforeseen conditions
(f) Nonpayment
(3) Prime contractor risks
(a) Underestimating costs (fixed price contract)
(b) Defective construction
(c) Nonperformance by its subcontractors and suppliers
(d) Unforeseen conditions
(e) Destruction of project during construction
(f) Insufficient/defective plans and specifications
(g) Performance being delayed: by owners notice to proceed, by
architects plans, by material from suppliers, and by owner deficiencies,
obstacles and problems
(h) Nonpayment
(i) Strikes
(j) Injuries to construction personnel and to third parties
(4) Subcontractor risks
(a) Defective plans and specifications
(b) Late receipt of plans and specifications, materials, equipment
(c) Interference
(d) Lack of access
(e) Defective performance
(f) Nonpayment
(g) Strikes
(5) Supplier risks
(a) Incorrect specifications
(b) Nonpayment
(c) Late delivery
(d) Defective goods
This list is obviously partial. Note that multiple parties
may have certain of the risks in common.
ii. The means of parties managing, allocating,
and transferring construction project risks.
Most construction project risks can be managed by contractual
provisions. All risks can be imposed upon one party or
distributed among all parties. However, a proposed allocation
may not be desirable: The burden of a risk may be placed
upon a party, but that party may not have the ability to control
or manage the risk, or the finances by which to cover the risk
if realized.
iii. What defines the management, allocation and transfer
of the construction project risks?
The rights and obligations of parties to a construction contract
include the assumption and acceptance of risks. In some
instances, the contract may transfer a risk that otherwise flows
to one party, to the second party. Generally, the rights
and obligations (include risk assumption and transfer) between
parties to a construction contract are defined and governed by
three sources:
(a) The agreement of the parties, written or oral (unless
the statute of frauds applies), express or implied.
(b) The law. Of course, the law is incorporated into every
contract, and, indeed, into every relationship. In the absence of agreement,
and sometimes in spite of agreement, the law totally governs. The
law includes applicable federal, state and local statutes, ordinances and regulations,
as well as the common law.
(c) The custom of the industry. Unless its application is negated by
the agreement of the parties, the custom of the industry to which the agreement
relates is incorporated into every contract, and into every relationship.
Furthermore, the rights and obligations of two parties may be
affected by provisions in a contract between one of the parties
and a third party. For example, a subcontract may incorporate
the contract between the owner and the prime contractor, or even
between the owner and the architect. The terms of that contract
may become terms of the subcontract and create additional rights
and obligations between the prime contractor and the subcontractor. Alternatively,
the contract between the owner and prime contractor, even if
not incorporated into the subcontract, may define the prime contractors
duties in ways which inure to the benefit (or detriment) of the
subcontractor. Examples include the duties to coordinate
subcontractors, establish schedules, and maintain safe working
conditions.
Because all these sources potentially impose contract obligations,
and because liability may attach to breaches of these obligations,
parties may wish to use the one source over which they have full
controltheir contractto manage, allocate and transfer
the kinds and degrees of risk that they undertake in entering
into an agreement. This article therefore explores the
use of contract clauses to both manage the risk assumed
by a party as well as to exculpateto free a party from
liability or responsibility or to transfer liability or responsibility. No
party should rely totally upon any contract clause to avoid liability
for every situation, especially where the clause might be perceived
by others or by the law as unfair or unreasonable. However,
in many instances, a contract may supersede the law in defining
the rights and responsibilities of parties, and thus may serve
as an effective tool to consciously manage risk.
This article explains how and why such clauses are useful in managing risk,
presents an example, and concludes with a discussion of enforceability. In
regard to enforceability, the discussions focus upon enforceability issues
endemic to each specific type of clause. Although there is no mention
of generic contract defenses, it should be noted that risk management clauses,
like any other contract clause, can be invalidated if they are the product
of mistake or of prohibited behavior such as fraud, dress, undue influence,
adhesion, etc.
iv. Risk management, allocation and transfer under the law.
As set forth above, in the absence of contractual provisions,
and sometimes in spite of contractual provisions, the law defines
the management, allocation and transfer of risks on a construction
project. A few examples.
Suppose the architect under the contract with the owner provides the drawings
that have defects. The owner provides these defective drawings to its
contractor. The contract between the owner and the contractor is silent
on the issue of defective drawings. The contractor suffers the risk
of defective drawings increased costs because of the defects. The law allows
the contractor to shift that loss to the owner: the law states that
the owner (generally) impliedly warrants the drawings, including constructability. The
law in turn allows the owner to shift the risk to the architect: recovery
of damages for breach of contract. But, this shifting does not enable
the owner to escape liability to the contractor; it only enables the owner
to have its loss reimbursed.
Should those risk transfers imposed by law be altered? Should the
contractors risk not be transferred to the owner? Should the contractors
risk be shifted directly to the architect? Should the owner not have a
right to transfer the loss from the architects negligence to the architect?
Usually, the law reflects what most people believe is the proper allocation
and transfer of risks; but in other circumstances the law does not reflect the
needs and abilities of specific parties. The means then becomes contractual
management, allocation and transfer of risk clauses.
b. Methods Of Management, Allocation And Transfer
Of Construction Project Risk
The most common, and usually most effective, method of management,
allocation and transfer of construction clauses is by the contract
terms between the parties. For example,
(a) There is a risk that the building being built will fall
down during construction, whether by reason of unusual wind,
fire, sabotage or negligent construction.
(b) The risk of the building collapsing during construction, for whatever
reason, is placed on the contractor.
(c) To provide financial strength to contractors undertaking this risk,
contractor must (a) provide a performance bond or
(b) obtain insurance which covers the risk.
Theoretically, this transfer of the risk to the contractor (which,
for the most part, already resides with the contractor under
law) costs nothing: the contractor includes in its bid
the cost of insurance or a bond, and the owner omits from its
budget those costs.
Thus, early questions in managing project risks include:
a. Who ought to bear the risk, and why?
b. Who (and how) can most economically bear the risk?
c. What impacts, if any, does transfer of risks have? Does it affect
control?
2. PROCEDURAL RISK MANAGEMENT, ALLOCATION AND TRANSFER CLAUSES
The first category of contract provisions that can be used to
manage, allocate and transfer risks of one party are procedural
clausesthose contract provisions that define the methods
and procedures to be followed should particular situations or
problems arise. In fact, such clauses can dramatically
affect the management, allocation and transfer of risks.
a. Choice Of Law Clauses
This Agreement shall be governed, interpreted and enforced in accordance with
the laws of the State of Colorado.
The laws of the several states differ; the laws of one state
may be more favorable to one party as to the distribution of
risks, whereas the laws of another state may be more favorable
to the other party; hence, in a multi-state transaction, the
rights and responsibilities of the parties may differ depending
upon which states law is applied to the transaction.
The simple example is the attitude of state laws toward contractual risk management,
allocation and transfer clauses: Some states are very liberal in enforcing
them. Others are very conservative, and construe them narrowly, or even
refuse to enforce certain ones. Thus, the choice of law clause may be
the most important of the clauses discussed herein.
If the parties make no provision, the applicable law will be chosen for them
by the court in accordance with the forum states often subjective choice-of-law
rules. E.g., UCC § 1-105(1) (transactions bearing an appropriate relation
to the forum state are subject to the states commercial code); Restatement
(Second) of Conflict of Laws § 6 (1971) (most significant
relationship); Farris v. ITT Cannon, 834
F. Supp. 1260 (D. Colo. 1993). Instead, parties can enhance the
predictability of their relationship by choosing the state substantive law
by which they prefer their relationship to be governed and their risks defined. For
example, if a contractor and subcontractor are both located in Colorado, but
the project is located in Wyoming, they may prefer to have their rights and
duties defined by more familiar Colorado law. Moreover, the parties could
even choose to have different issues in their contract governed by different
laws. See generally Restatement
(Second) of Conflict of Laws § 187, comment i.
Of course, choice of law clauses cannot be utilized to frustrate the forums
public policy as to remedies. Cf., Mitsubishi
Motors Corp. v. Soler Chrysler - Plymouth, Inc., 473 U.S. 614, 637 n.19
(1985).
Enforceability: Generally, choice of law provisions
are held binding and enforceable. Hansen
v. GAB Business Services, Inc., 876 P.2d 112 (Colo.
App. 1994); Lauritzen
v. Larsen, 345 U.S. 571, 588-89 (1953); Seeman
v. Philadelphia Warehouse Co., 274 U.S. 403, 407 (1927). The
key limitation is that the chosen state must bear a reasonably
close relationship to either the parties or the transaction. Restatement
(Second) Conflict of Laws § 187; UCC § 1-105(1)
(1989). Courts consider a number of factors in discerning
whether the requisite relationship exists, including the parties principal
place of business, place of incorporation, location of the contracted
property, place of execution, place of performance, place of
payment, and purpose of the contract. A. Covey & M. Morris, The
Enforceability of Agreements providing for Forum and Choice of
Law Selection, 61 Den. L. J. 837, 854-55 (1984).
Although the case by case method and subjective nature of this inquiry infuses
some uncertainty regarding the provisions enforceability, the reasonable
relationship test is easily met in most cases. Parties normally
will not choose a states substantive law unless they have some meaningful
relationship with the chosen state. Thus, one or more of the factors
listed above will be present, and a reasonable relationship will exist.
b. Forum Selection Clauses
The parties hereby agree that any dispute between them will be resolved, if
legally possible, in a state court located within the City and County of Denver,
State of Colorado.
See Packaging Store,
Inc. v. Leung, 917 P.2d 361 (Colo. App., 1996). (The
defendant also appointed the Corporation Company in Colorado
as its agent for service of process).
In the event that any
dispute shall arise with regard to any provision or provisions of this Agreement . . . Jurisdiction
shall be in the State of Colorado, and venue shall lie in the County of El Paso,
Colorado.
Cf., Excell, Inc. v.
Sterling Boiler & Mechanical Inc., 106 F.3d 318 (10th
Cir. 1997). (Held mandatory jurisdiction in the El Paso
County District Court, and not a Colorado Federal District Court.)
No alteration, change,
addition or deviation shall be made from that shown or described in the contract
documents, except upon the execution by both parties of a written change order.
One of the risks of a construction project is the high cost of litigating a
dispute because of the location of the forum. In addition to choosing
the applicable substantive law, parties may select the particular forum for
litigating any disputes. For example, a project may be located in Arapahoe
County, but if the parties are based in Denver County, they might prefer that
all disputes be decided by a court located in Denver. Assuming federal
jurisdictional requirements are met, they may even select between a federal
or state court located in Denver.
More commonly, a forum selection clause is used when a party
who is participating in a project out of state desires that any
controversy that arises be litigated in his home state. Similarly,
an owner who is subject to jurisdiction of various states might
want all controversies regarding the project to be resolved in
the state where the project is located. Often the time
spent traveling to the locality of the court is extensive. Thus,
it is very important to the parties that disputes be resolved
in a convenient forum.
Enforceability: See Riley v. Kingsley Underwriting
Agencies, Ltd., 969 F.2d 953 (10th Cir. 1992), cert. denied,
506 U.S. 1021 (1992).
c. Notice Clauses
The Owner shall not be liable to the Contractor for damages caused by delay,
by any reason whatsoever, unless the Contractor gives notice of the delay to
the Owner within five business days after the cause of the delay occurs.
The contractor shall not be entitled to an extension of time or to additional
compensation or damages, unless the contractor submits a written request to
the owner within seventy-two (72) hours after the event giving rise to the
request. The request shall set forth all facts upon which the request
is based, together with all supporting documents.
The essence of a notice clause is that notice of some act or intended action
is a condition precedent to liability.
There are multiple potential benefits to and reasons for notice clauses:
(i) The party who will be liable should have an opportunity
to investigate the facts while the facts are fresh.
(ii) A party should be required to decide whether to assert or not assert a
claim promptly.
(iii) The progress of a job depends upon everyone knowing where everyone else
stands.
Other examples of notice provisions that you should consider
inserting into contracts include:
Any claim by the parties that arises out of or in connection with this Agreement
shall be barred, unless a notice thereof is given to the other party within
one month after the date of the act or omission that gave rise to such claim.
Enforceability: Most notice provisions are valid,
so long as the time is reasonable. The principal problem
is usually whether the court will construe the clause to apply
to a particular situation. See
generally, 17A Am. Jur. 2d Construction
Contracts.
d. Contractual Statutes of Limitation
Any claim arising out of or in connection with this Agreement shall be asserted
by a complaint in a civil action commenced within eight months after the claim
arose, and, if not, shall thereafter be barred.
All states have statutory time limits within which a party may be sued by another
party. For a relevant example, the statute of limitations in Colorado
for most construction claims is C.R.S. ' 13-80-104. Sometimes the parties
desire to shorten that period of time in order to insure that they are safe
from the threat of litigation sooner than provided by state law. A construction
project must come to an end, including the claims that arise therein. There
is little benefit to permitting a party to delay asserting a claim, unless
the party does not know of the claim.
Enforceability:The courts generally enforce such a clause
even though the statutory period of limitation or period of repose
may be substantially longer -- so long as reasonable. See
Hepp v. United Airlines, Inc., 540 P.2d 1141 (Colo.
App. 1975).
e. Mediation Clauses
If a dispute arises out of or relates to this contract, or the breach thereof,
and if the dispute cannot be settled through negotiation, the parties agree
first to try in good faith to settle the dispute by mediation administered
by the American Arbitration Association under its commercial mediation rules
before resorting to arbitration, litigation or some other dispute resolution
procedures.
American Arbitration Association Mediation clause.
A mediation clause can pressure one party to compromise, and
ultimately accept less than litigation would have awarded. Mediation
is a process whereby the parties, with the assistance of a neutral
third party, negotiate a resolution to their differences. Mediation,
in many instances, has been extremely effective in resolving
contract disputes, thus avoiding the time, energy and cost of
arbitration or litigation. Nevertheless, it may result
in fewer or more benefits to one of the parties.
Enforceability: Even when parties assert that
they are going to refuse to settle, the courts recognize that,
in fact, settlements and compromises are often obtained through
mediation notwithstanding the parties predisposition. Thus,
although mediation, unlike arbitration, concludes a dispute
only through agreement of the parties, courts generally enforce
a mandatory mediation clause.
f. Arbitration Clauses
Any controversy or claim arising out of or relating to this contract, or the
breach thereof, shall be settled by arbitration administered by the American
Arbitration Association under its commercial arbitration rules, and judgment
on the award rendered by the arbitrator may be entered in any court having
jurisdiction thereof.
An arbitration clause may manage risks and substantially affect the allocation
and transfer/elimination of risks. For example, under Colorado law
an arbitrator cannot award punitive damages. C.R.S. § 13-21-102(5)
(Probably not applicable to arbitrations governed by Federal Arbitration
Act, 9 U.S.C. § 1, et seq.). This may eliminate the risk
to the parties of suffering punitive damage awards. (On the other hand,
this may simply mean a separate judicial proceeding must be held as to punitive
damages. See generally, Mulder
v. Donaldson, Lufkin & Jenrette, 648 N.Y.S. 2d 535 (App. Div.
1996).)
Does arbitration change the ultimate bearer of the risk? Is
the amount of liability of a defendant less in arbitration than
in a court or jury trial? Is the likelihood of a defendant
even being found liable greater or lesser in an arbitration than
in court trials? Many believe the answer is yes. If
so, an arbitration clause is a substantial tool in the management,
allocation and transfer of risks.
In Mastrobuono v. Shearson Lehman Hulton
Inc., 115 S. Ct. 1212, 1217-19 (1995), the United States Supreme
Court held that punitive damages could be precluded by a choice of law rule,
at least when the Federal Arbitration Act is applicable.
A related consideration is whether parties desire arbitration in lieu of litigation
to resolve disputes. The subject of the pros and cons of arbitration
is not here to be covered in depth. However, main considerations are:
g. Waiver Of Trial By Jury
In the event a dispute arises out of or in connection with this Agreement,
the parties agree that it shall be tried to a judge without a jury, and expressly
waive any right to a trial by jury.
or
Each party to this Agreement hereby expressly waives any right to trial by
jury of any claim, demand, action or cause of action (1) arising under this
Agreement or any other instrument, document or agreement executed or delivered
in connection herewith, or (2) in any way connected with or incidental to the
dealings of the parties hereto or any of them with respect to this Agreement
or any other instrument, document or agreement executed or delivered in connection
herewith, or the transaction related hereto or thereto, in each case whether
now existing or hereafter arising or whether sounding in contract or tort or
otherwise; then each party hereby agrees and consents that any such claim,
demand, action or cause of action shall be decided by court trial without a
jury, and that any party to this Agreement may file an original counterpart
or copy of this section with any court as written evidence of the consent of
the parties hereto to the waiver of their right to trial by jury.
Weissman, Lender Liability: How
to Protect Yourself Against Unwarranted Suits 101 (1988), quoted in
Rusoff, Contractual Jury Waivers: Their Use in Reducing Lender
Liability, The Banking Law Journal, January/February 1993, p. 6.
Are liabilities and damages affected by whether a judge or a jury determines
them? Many would say yes.
Enforceability: Most jurisdictions uphold the validity
of a jury waiver clause. See
generally, Anno., Contractual Waiver of Jury Trial, 73 A.L.R.2d
1332 (1960).
h. No Discovery Clauses
In the event of litigation between the parties, the parties agree that there
shall be no discovery of any nature, whether written or oral.
Obviously, one party can usually benefit by the other partys not having
a right of discovery. Many believe that discovery, or the lack thereof,
can substantially affect the outcome of litigation. On the other hand,
eliminating discovery can also substantially reduce the cost of litigation.
The basic rule of enforceability was defined in Developments in the LawDiscovery, 74
Harv. L. Review 940, 979, n.301 (1991):
A court may refuse to enforce a contract limiting discovery if it is unconscionable. This
would depend on the inequality of the parties bargaining power, the scope
of the restriction imposed, and the stage in the parties relationship
in which the agreement is made. Thus if it is made after the cause of
action accrues, both parties will presumably be aware of the issues to be proved
and the facts that must be uncovered. Such an agreement is therefore
more likely to be upheld than one made, for example, at the beginning of a
course of business dealings, before the parties have any idea of their respective
obligations of proof in a lawsuit not yet materialized. . . . For
the same reasons, a limitation of discovery in a contract for a single business
transaction is much more likely to deal with foreseeable and specific problems
of disclosure than is a contract made with a view to a long period of business
dealings.
See also C.R.S. § 4-2-302 (unconscionable contract or clause in sales
contract).
i. Summary Of Procedural Clauses
The foregoing clauses, when properly drafted for the particular circumstances,
can have a substantial impact upon the risks of each party to the Agreement. Should
such clauses be used, and whether they are enforceable, must wait a few pages.
3. DAMAGE LIMITATION CLAUSES
Each party is interested in limiting the liability that it might have to another
party. Damage limitation clauses can serve the useful function of circumscribing
the scope of a partys liability and of providing more certainty regarding
the outer boundaries of a partys potential monetary risk.
a. Limitations On Types Of Damages For Which A Party Can Be
Liable
One effective method of limiting exposure is to place restrictions on the kinds
of recoverable damages. There are several categories of damages, having
varying probabilities of enforceability, that are possible candidates for limitations.
b. Limitations On Recovery Of Incidental And Consequential
Damages
The parties stipulate and agree that neither party shall be liable to the other
for any incidental or consequential damages of whatsoever nature, however caused,
whether by the negligence of the party or otherwise.
One type of clause would limit liability for incidental or consequential damages. The
UCC defines incidental damages as including expenses reasonably incurred in
inspection, receipt, transportation and care and custody of goods. Consequential
damages are defined as losses resulting from particular requirements and needs
of a buyer made known to the seller. See
also Haynes & Boone v. Browser Bouldin, Ltd., 896 S.W.2d 179, 182
(Tex. 1995); McAlister v. Citibank, 829
P.2d 1253, 1257 (Ariz. 1992).
An example of incidental or consequential damages is where an owner contracts
to have a motel built, and the motel is not finished on time. Incidental/consequential
damages could be the money the motel owner loses by his inability to rent rooms
due to late completion.
Another example of limitation of liability for consequential
damages might read:
Neither party to this agreement shall be liable for any special, indirect,
incidental or consequential damages of any nature, including, without limitation,
loss of profits, loss by reason of shutdown, and loss of use or interest.
The EJCDC consequential damage limitation clause provides:
Owner hereby agrees that to the fullest extent permitted by law Design Professional
shall not be liable to the owner for any special, indirect or consequential
damages whatsoever, whether caused by the Design Professionals negligence,
errors, omissions, strict liability, breach of contract, breach of warranty
or other cause or causes whatsoever, including but not limited to (list here
particular types of consequential damages that Design Professional may be concerned
about by reason of the nature of the project, e.g., costs of replacement power,
loss of use of equipment or facility, loss of profits or revenue, etc.).
See EJCDC Doc. No. 1910-9E (1986).
Enforceability: Cf. C.R.S. § 4-2-719 (UCC). Generally,
a no consequential damages clause is valid and enforceable. However,
in Cooley v. Big Horn Harvestore Systems, 813 P.2d 736 (Colo. 1991), our
Supreme Court said with respect to contracts subject to the UCC:
[W]hile contracting parties may generally limit the remedies available in the
event of foreseeable and bargained-for contingencies, when a limited remedy
fails of its essential purpose any contractual limitation directly related
to the assumption that the limited remedy constituted a sufficient remedy must
also fail.
813 P.2d at 747. However, the Court did seem to leave open the validity
of a clear and unambiguous exclusion of consequential damages even if the remedy
provided fails of its essential purpose. Id. at 748.
c. Liquidated Damage Clause
If either of the parties to this Agreement fails to comply with the terms and
conditions of this Agreement or to carry out any provisions of this Agreement
by such party to be performed, such party shall pay to the other the sum of
$10,000 as liquidated and agreed damages.
Enforceability: In Colorado, a liquidated damage
clause is valid and enforceable, if
1) the anticipated damages are uncertain in amount
or difficult to prove;
2) the parties intended to liquidate the damages in advance of occurring;
3) the amount stated is a reasonable amount, i.e., not greatly disproportionate
to the presumable loss or injury.
Perino v. Jarvis, 312 P.2d
108 (Colo. 1957).
d. Punitive Damages:
The parties agree that neither shall have liability to the other for punitive
(exemplary) damages unless the wrongdoers liability arises from the partys
intentional wrongdoing.
or
Neither party shall be liable to the other for punitive (exemplary) damages.
or
The arbitrator(s) shall not have jurisdiction or authority to award punitive
(exemplary) damages.
Punitive damages are another type of damages that the parties may consider
limiting. In general, most states allow an award of punitive damages
are only for grossly negligent, willful, wanton or intentional wrongs. See
C.R.S. § 13-21-102.
Enforceability: Many courts refuse to enforce
a clause that eliminates recovery of punitive damages for intentional
wrongdoing on the grounds of public policy. See Restatement
(Second) Torts § 195, 500; Winterstein
v. Wilcom, 293 A.2d 821 (1972). On the other hand,
a court may very well enforce such a clause that precludes liability
for punitive damages for simple grossly negligent conduct.
Similarly, a prohibition upon the award of punitive damages by an arbitrator
may be interpreted as meaning only that the punitive damage aspect of a claim
must be decided by a court. See Mulder
v. Donaldson, Lufkin & Jenrette, 648 N.Y.S. 2d 535 (App. Div. 1996).
e. Specific Occurrences: No Damage For Delay
Contractor shall not be liable to Subcontractor for any delay to Subcontractors
performance of its work caused by the act or omission of the Owner or Architect,
or by any act beyond the Contractors control.
or
If Contractors performance is delayed by [non-negligent] acts of the
Owner or by events beyond the Contractors control, the Contractor shall
be entitled, upon request, to a reasonable extension of time for performance,
but shall not be entitled to an increase in compensation or to damages by reason
of the delay.
A party may also attempt to avoid liability for specific types of occurrences. For
example, perhaps the most common limitation of damage clause in the construction
industry is the no damage for delay clause. Neither party shall be liable to
the other for damages for any delay arising out of clauses beyond its reasonable
control and without its fault or negligence.
In Colorado, governmental bodies are prohibited by statute from including no
damage for delay clauses in their contracts. C.R.S. § 24-91-103.5(1)(a).
Enforceability: In general, the courts are reluctant
to automatically enforce no damage for delay clauses. C.R.S.
' 24-91-103.5(1)(a) relating to public works contracts provides
that a provision releasing or extinguishing the right of a contractor
to recover for a delay from a public entity is void as against
public policy. See
Anno., No Damages for Delay Clauses, 74 A.L.R.3d
187 (1976). The most successful arguments to avoid the
application of the clause appear to be (1) the delay was caused
by the active interference (omission) of the owner; (2) the
delay was from a cause not contemplated by the parties when entering
into the agreement; and (3) the delay is not within the
specific wording of the clause.
f. Limitations On Amounts Of Damages For Which A Party Can
Be Held Liable
The parties stipulate and agree that the liability of each party to the other
as to claims arising out of or in connection with the subject matter of this
contract shall be limited to $50,000.
The parties may agree to simply place a limitation on the amount of damages. For
example, if a party enters into a $100,000 contract, perhaps neither side is
willing to be exposed to more than $50,000 in liability. Such a clause
might read:
12.2.1 Compensation. Neither the architect,
the architects consultants, nor their agents or employees
shall be jointly, severally or individually liable to the owner
in excess of the compensation to be paid pursuant to this agreement
or of ________________ Dollars ($_____), whichever is greater,
by reason of any act or omission, including breach of contract
or negligence not amounting to a willful or intentional wrong.
AIA Doc. B511, Guide for Amendments to AIA Document B141 (1993 Ed.).
Similarly, the EJCDC suggested clause reads as follows:
Owner hereby agrees that to the fullest extent permitted by law Design Professionals
total liability to Owner for any and all injuries, claims, losses, expenses
or damages whatso-ever arising out of or in any way related to the project
or this agreement from any cause or causes including but not limited to Design
Professionals negligence, errors, omissions, strict liability, breach
of contract or breach of warranty shall not exceed the total compensa-tion
received by Design Professionals under this agreement.
EJCDC Doc. 1910-9E (1986).
This clause can be made more effective if it provides that the owner can pay
designated sums (e.g., for insurance) so as to not have the liability so limited. In
other words, the parties should emphasize that the limited liability was a
bargain for term based upon costs.
Similarly, damages can be limited to insurance:
12.2.1 Insurance. Neither the architect, the
architects consultants, nor their agents or employees shall
be jointly or individually liable to the owner in any amount
in excess of the currently maintained professional liability
insurance coverage carried by the architect.
AIA Doc. B511, Guide for Amendments to AIA Document B141 (1993 Ed.).
The EJCDC limitation
of liability to specific dollar amount provides:
Owner hereby agrees that to the fullest extent permitted by law Design Professionals
total liability to Owner for any and all injuries, claims, losses, expenses or
damages whatso-ever, arising out of or in any way related to the project or this
agreement for any cause or causes including but not limited to Design Professionals
negligence, errors, omissions, strict liability, breach of contract or breach
of authority shall not exceed the total amount of $_______.
See EJCDC Doc. 1910-9E (1986). Special care must be exercised in utilizing
such a clause. For example, there may be a desire to make the damage limitation
inapplicable if the claim is for indemnity. Thus, if the prime contractor
is sued by a third party for acts in fact committed by the subcontractor for
which the prime contractor is responsible, the prime contractor may not wish
any limitation on the amount he can recover or wrongs for which his liability
is premised solely on respondeat superior.
Enforceability: In general, limitations on the amount
of damage clause would be upheld. See Estey v. MacKenzie Engineering,
Inc., 902 P.2d 1220 (Ore. 1995); Contra, Ricciardi v. Frank,
620 N.Y.S.2d 918 (N.Y. City Ct. 1994) (failure to state clauses relieved
engineer of own negligence). However, public policy grounds
may invalidate such clauses in certain circumstances, including if
the restriction is to sever. See generally, Weld v. Postal
Telegraph Cable Co., 92 N.E. 415 (N.Y. 1910) and infra.
g. Attorney Fees And Costs
In the event of litigation arising out of or in connection with this Agreement
between the parties hereto, the prevailing party shall be entitled to recover
reasonable attorneys fees and expenses incurred in the prosecution or defense
thereof.
Attorney fees clauses are universally upheld.
h. Exculpatory Clauses: No Liability For Negligence
The Parties agree that neither party shall be liable to the other in negligence,
other legal theory (except for breach of contract and willful, wanton or intentional
conduct) for acts or omissions arising out of the subject matter of this contract.
The parties may agree that Party A will not be liable to Party B for Party As
negligence.
Enforceability: A term exempting a party from
tort liability for harm caused intentionally or recklessly is unenforceable
on grounds of public policy. Restatement (Second) Contracts § 195
(1981); Restatement (Second)
Torts§ 500 (1965). [A]greements attempting
to exculpate party from his or her own negligence have been upheld
under certain circumstances . . . . In
determining whether an exculpatory agreement is valid, there are
four factors that a court must consider: (1) the existence
of a duty to the public; (2) the nature of the service performed;
(3) whether the contract was fairly entered into; and (4) whether
the intention of the parties is expressed in clear and unambiguous
language. Riehl
v. B&B Lively, Inc., ___ P.2d ___, 1997 WL 94053 (Colo.
App. Mar. 6, 1997).
On the other hand, C.R.S. 13-50.5-102(8) provides that public construction contracts
that contain a clause holding the public entity harmless from its own negligence
is void as against public policy. It expressly provides that it affects
only the indemnity of the public entity, and does not apply to insurance or to
bonds covering such liability. See also Murray, The Validity of Exculpatory
Clauses in Architectural Services Contracts, 25 Colo. Lawyer 39 (March 1996).
i. Indemnity Clauses
The parties stipulate and agree that each shall be liable to the other by reason
of acts or omissions arising out of or in connection with this Agreement solely
if the conduct of the party asserted to be liable is willful, wanton or intentional. Neither
party shall be liable to the other for its own negligence, breach of contract,
or other claim that does not constitute a willful, wanton or intentional act.
Subcontractor agrees to indemnify and hold Contractor harmless from any loss,
damage or expense arising out of or in connection with [to the extent resulting
from] any act or omission of Subcontractor.
Technically, an indemnity should relate to the acts of a third party. The
law and the contract define the liability of a party, and it serves little purpose
for the first party to agree to indemnify the other for that for which the first
party is already liable.
j. Mechanics Lien
Pursuant to C.R.S. 38-22-119, Contractor hereby waives and relinquishes any right
to a mechanics lien it may hereafter have. Contractor further agrees
to similarly so provide in its subcontracts for the benefit of the Owner.
4. ALLOCATION OF COST OF COVERING RISKS
Any party doing construction projects has the risk of potential loss. Obviously,
prime contractors risk (fixed-price contract) includes the risk of cost
overrun. Any kinds of risks that a party might have under law can potentially
be reallocated by the contract. For example, a cost-plus contract, depending
upon the kind and types of costs that are , reallocates many risks.
a. Insurance Coverage
Upon written request of Owner received within five days of acceptance hereof,
Engineer will provide additional insurance, if available. Engineers
liability to Owner for any indemnity commitments or for any damages arising in
any way out of the performance of this Contract is limited to such insurance
coverages and amounts. In no event shall Engineer be liable for any indirect,
special or consequential loss or damage arising out of the performance of services
hereunder including, but not limited to, loss of use, loss of profit, or business
interruption whether caused by negligence of engineer, or otherwise and Owner
shall indemnify and hold engineer harmless from any such damages or liability.
This clause was upheld in Florida Power & Light
Co. v. Mid-Valley, Inc., 763 F.2d 1316 (11th Cir. 1985). See
Markborough California, Inc.v. Superior Court, 227 Cal. App.3rd 705 (1991). Requirements
for a valid limitation of liability clause may include proof that it was in fact
negotiated, a definite limitation amount, and an unambiguous description of precisely
the risk which it covers. See also
Anderson, Contractual Limitations on Remedies, 67 Neb. Law Rev. 548 (1988).
One of the most common means of risk allocation is to provide that the owner
will carry certain kinds and types of insurance coverage and that all contractors
and subcontractors, etc., shall be named as additional insureds thereof. This
affords a substantial benefit. Most owners would want to have basic coverage
regardless of what the contract defined as his responsibility. This can
have a result where the owner, the prime contractor and the subcontractor all
buy in essence the same insurance coverage and thereby increase the total cost
of the project. Its usually desirable to have one party carry the
insurance coverage and all parties to the project benefit therefrom.
Examples of such insurance coverage could potentially include builders risk,
comprehensive general liability, and professional errors and omissions.
Contractors aggregate liability arising out of or in connection with this
agreement, regardless of the theory of recovery, shall not exceed the amounts
of insurance required by this Agree-ment to be maintained, except as to claims
arising from damages caused by Contractors willful and wanton or intentional
misconduct.
b. Site Investigation
Each responsibility can be specifically defined by the contract, and obviously,
most instances are. For example, should a contractor be invited to rely
upon the soils investigation performed by the soils engineer hired by the owner. It
may not seem logical to have multiple soils engineers testing the soil, and it
escalates the cost.
c. Indemnification
3.18.1. To the fullest extent permitted by law, the
Contractor shall indemnify and hold harmless the Owner, architect,
architects consultants, and agents and employees of any of
them from and against claims, damages, losses and expenses, including
but not limited to attorneys fees, arising out of or resulting
from the performance of the Work, provided that such claim, damage,
loss or expense is attributable to bodily injury, sickness, disease
or death, or to injury to or destruction of tangible property (other
than the Work itself) including loss of use resulting therefrom,
but only to the extent caused in whole or in part by negligent acts
or omissions of the Contractor, a Subcontractor, anyone directly
or indirectly employed by them or anyone for whose acts any of them
may be liable, regardless of whether or not such claim, damage, loss
or expense is caused in part by a party indemnified hereunder. Such
obligation shall not be construed to negate, abridge, or reduce other
rights or obligations of indemnity which would otherwise exist as
to party or person described in this Paragraph 3.18.
3.18.2. In claims against any person or entity indemnified
under this paragraph 3.18 by an employee of the Contractor,
a Subcontractor, anyone directly or indirectly employed by them or
anyone for whose acts they may be liable, the indemnification obligation
under this Paragraph 3.18 shall not be limited by limitation
on the amount or type of damages, compensation or benefits payable
by or for the Contractor or a Subcontractor under Workers or
Workmens Compensation Acts, Disability Benefit Acts or other
employee benefit acts.
3.18.3. The obligations of the Contractor under this
Paragraph 3.18 shall not extend to the liability of the Architect,
the Architects consultants, and agents and employees of any
of them arising out of (1) the preparation or approval of maps,
drawings, opinions, reports, surveys, Change Orders, designs or specifications,
or (2) the giving of or the failure to give directions or instructions
by the Architect, the Architects consultants, and agents and
employees of any of them provided such giving or failure to give
is the primary cause of the injury or damage.
AIA Document A201, General Conditions of the Contract for Construction (1987
Ed.).
Contractor agrees that
it shall indemnify and hold Owner harmless from and against any loss, damage,
or expense arising out of or in connection with this project that arises prior
to the issuance of the certificate of occupancy. This indemnity shall apply
to Owners negligence, but not to its intentional, willful or wanton wrongful
acts or omissions. Contractor recognizes and acknowledges that the intent
of the parties is to place all risks of the project upon Contractor, except those
arising from Owners intentional willful or wanton wrongful acts or omissions.
Does this clause say anything more than that the contractor shall pay the Owner
for any amounts for which the contractor is liable in law? But, liability
is imposed for 100% of the loss even if the contractors liability was a
part of the cause. Does this negate or incorporate the Colorado Pro Rata
Liability statute, if applicable? Id., Comparative Negligence Statute.
On the other hand, the parties might in essence agree to indemnification equivalent
to that provided by the Colorado Comparative Negligence statute and the Contribution
statute. For example:
Contractor shall indemnify and hold indemnitee harmless from and against all
claims, damages, losses and expenses arising out of or in connection with the
performance of the work, but only to the extent caused in whole or in part by
the negligent acts or omissions of the indemnitor.
On the other hand, in dealing with public entities, one should
be familiar with C.R.S. 13-50.5-102, which provides:
13-50.5-102. Right to contribution - contract or agreement
provision to indemnify or hold harmless void against public policy.
(8) In the event that a public contract or agreement
for the construction, alteration, repair, or maintenance of any
building, structure, highway bridge, viaduct, water, sewer, or
gas distribution system, or other works dealing with construction,
or any moving, demolition, or excavation connected with such construction,
contains any covenant, promise, agreement, or combination thereof
to indemnify or hold harmless any public entity from that public
entitys own negligence, then such covenant, promise, agreement,
or combination thereof is void as against public policy and wholly
unenforceable. This subsection (8) shall not apply to construction
bonds, contracts of insurance, contract clauses regarding insurance,
or contract clauses regarding costs of defense of litigation arising
out of the work or to any covenant, promise, agreement, or combination
thereof to indemnify or hold harmless a contracting party against
claims arising out of the negligent acts of the indemnitor and
its subcontractors in the performance of the work under the contract. However,
no contracting party shall be required to indemnify or hold harmless
from any liability or damages arising from the negligent acts of
the indemnified party. This subsection (8) is intended only
to affect the contractual relationship between the parties relating
to indemnification of public entities for the negligent acts of
the public entity, and nothing in this subsection (8) shall affect
any other rights or remedies of public entities or contracting
parties.
The Engineers Joint Contract Documents Committee (EJCDC)
standard general conditions of the construction contract (Doc. No. 1910-8)
have a somewhat different indemnification provision.
6.31. To the fullest extent permitted by Laws and
Regulations, CONTRACTOR shall indemnify and hold harmless OWNER,
ENGINEER, ENGINEERs Consultants and the officers, directors,
employees, agents and other consultants of each and any of them
from and against all claims, costs, losses and damages (including
but not limited to all fees and charges of engineers, architects,
attorneys and other professionals and all court or arbitration
or other dispute resolution costs) caused by, arising out of
or resulting from the performance of the Work, provided that
any such claim, cost, loss or damage: (i) is attributable
to bodily injury, sickness, disease or death, or to injury to
or destruction of tangible property (other than the Work itself),
including the loss of use resulting therefrom, and (ii) is
caused in whole or in part by any negligent act or omission of
CONTRACTOR, any Subcontractor, any supplier, any person or organization
directly or indirectly employed by any of them to perform or
furnish any of the Work or anyone for whose acts any of them
may be liable, regardless of whether or not caused in part by
any negligence or omission of a person or entity indemnified
hereunder or whether liability is imposed upon such indemnified
party by Laws and Regulations regardless of the negligence of
any such person or entity.
6.32. In any and all claims against OWNER or ENGINEER
or any of their respective consultants, agents, officers, directors
or employees by any employee (or the survivor or personal representative
of such employee) of CONTRACTOR, any Subcontractor, any Supplier,
any person or organization directly or indirectly employed by
any of them to perform or furnish any of the Work, or anyone
for whose acts any of them may be liable, the indemnification
obligation under paragraph 6.31 shall not be limited in
any way by any limitation on the amount or type of damages, compensation
or benefits payable by or for CONTRACTOR or any such Subcontractor,
Supplier or other person or organization under Workers Compensation
Acts, Disability Benefit Acts or other employee benefit acts.
6.33. The indemnification obligations of CONTRACTOR
under paragraph 6.31 shall not extend to the liability of ENGINEER
and ARCHITECT and ENGINEERs Consultants, officers, directors,
employees or agents caused by the professional negligence, errors
or omissions of any of them.
Obviously, the EJCDC document was drafted after the AIA document paragraph 4.18.
As to the AIA Subcontract Indemnification Provision, see AIA Doc. A401, Standard
Form of Subcontract Agreement between Contractor and Subcontractor, Section 4.6.
An example of a required insurance clause is contained in AIA Doc. A201,
Article 11. In brief, this provision requires the Contractor to
maintain insurance for workmens compensation, bodily injury, etc., of
contractors employees, third party claims for bodily injury, and in general
all damage to person or property caused by the contractor. Article 11.2
is the owners liability insurance.
The liability of the contractor to the owner (or the subcontractor to the contractor)
in turn can be limited to the insurance carried.
Notwithstanding any other provision herein, the liability of the Contractor
to the Owner shall in no regards exceed or be outside the insurance to be carried
by the Contractor pursuant to the terms hereof.
Alternatively:
12.2 Insurance. Neither the architect, the architects consultants,
or their agents or employees shall be jointly or individually liable to the
owner in an amount in excess of the currently maintained professional liability
insurance coverage carried by the architect.
AIA Doc. B511, Guide for Amendments to AIA Doc. B141 (1993 Ed.).
Enforceability: Indemnification clauses are generally
valid and enforceable. It is when the indemnification includes
indemnification of the negligent party for his own negligence
that most problems arise. Many states have adopted anti-indemnification
statutes. However, very generally, even such indemnification
clauses are valid if properly worded. See Halpern, Indemnity
Provisions in Construction Contracts, Construction
Law Advisor (Sept. 1988). See Section III, H. supra. Perhaps
the best way to provide this risk transfer is by a policy of
insurance covering, inter
alia, the risk, and the contract defining who pays the
premium.
d. Performance Bonds
Performance bonds are required by statute, code or ordinance by many governmental
entities. In general, to the extent the contractor (or its subcontractors)
fails to perform the contract, the surety is monetarily liable for performance. In
short, it is analogous to insurance. However, whereas an insured does
not have to reimburse the insurer for losses sustained, the principal does
have to reimburse the surety. Thus, in fact the performance bond ordinarily
does not shift risk.
5. SHOULD YOU USE THE RISK ALLOCATION AND TRANSFER CLAUSES?
So, you have reviewed and considered the risk allocation and transfer clauses
outlined above, and a lot of others. And, you and your client like
some of them, and maybe all of them. Should you incorporate them
into your next construction contract?
a. Are The Clauses Valid And Enforceable?
As discussed above, all of the clauses in particular circumstances probably
are valid and enforceable. However, in specific circumstances,
which may include the circumstances of your client, any of the clauses may
be void/voidable or unenforceable. The following is a brief discussion
of the basic theories pursuant to which risk management and transfer clauses
may be held invalid in any particular circumstances.
Cooley v. Big Horn Harvestore
Sys., 813 P.2d 736, 744-45 (Colo. 1991) established the
basic principle that a limitation of remedy fails of its
essential purpose and is therefore void, if it operates
to deprive a party of the substantial value of the contract.
i. Duress.
Duress is usually easy to understand but difficult to defend. Generally,
duress is compulsion (such as to execute a contract) caused by threats that
destroy freedom of will. One court has described duress as the result
of unlawful threats resulting in a contract essentially unjust toward the party
seeking relief from it. McClair
v. Wilson, 18 Colo. 82, 85 (1892). See 25
Am. Jur. 2d, Duress and Undue Influence, describing
the elements as (1) one side involved fairly accepted the terms of another,
(2) the circumstances permitted no other alternative, and (3) the circumstances
were the result of coercive acts of the opposite party. See
particularly § 6, economic duress.
ii. Unconscionability.
E.g., C.R.S. 4-2-301 (uncon-scionable contract or clause in sales contract). Under
the U.C.C., unconscionability has been defined as when the provision defeats
the reasonable expectation of the parties. Leprino v. Intermountain Brick
Co., 759 P.2d 835 (Colo. App. 1988); Viner v. Brockway, 36 Cal. Rptr.2d 718
(Cal. App. 1994) (limitation of liability clause unconscionable); Valhal Corp.
v. Sullivan Associates, Inc., 44 F.3d 195 (3d Cir. 1995) (upholding limitation
on liability clause).
iii. Against public policy.
In Stanley v. Creighton Co., 911
P.2d 705 (Colo. App. 1996), the court declared void as against public
policy an exculpatory clause in a residential rental agreement that relieved
the landlord of liability for all but gross negligence. See
Viner v. Brockway, supra.
In Jones v. Dressel, 623 P.2d 370, 376 (Colo. 1981),
the court formulated a four factor test to determine the validity
of exculpatory clauses:
- Existence of a duty to the public
- Nature of the service performed
- Whether the contract was fairly entered into, and
- Whether the intention of the parties is expressed in clear
and unambiguous language.
See also 57 Am. Jur. 2d Negligence § 52.
iv. Contract of adhesion.
In Bauer v. Aspen Highland Skiing Corp., 788
F. Supp. 472 (D. Colo. 1992), a skier sued the equipment manufacturer, rental
shop and ski school for injuries suffered. A part of the ski rental agreement
contained the following language which pointed out that skiing is a hazardous
activity, that injuries are common, the ski boot binding system cannot release
to prevent injuries at all times and under all circumstances, etc. It
then concluded:
I hereby RELEASE the ski shop and its owner, agents
and employees, Marker and its owners, agents and employees from
any and all liability for injuries or damage to the user of equipment
listed on this form or to any other person, resulting from NEGLIGENCE,
the selection, installation, maintenance, adjustment, and use of
this equipment. In addition, they shall not be held liable
for any consequential damages. I agree NOT to make a claim
against or sue this ski shop or Marker for injuries or damages
relating to skiing and/or the use of this equipment.
788 F. Supp. at 472. The court applied the four factors of the Jones case. With
respect to the assertion that it was a contract of adhesion:
Colorado defines an adhesion contract as generally
not bargained for, but imposed on the public for a necessary service
on a take it or leave it basis. Jones, 623 P.2d at
374. However, printed form contracts offered on a take it
or leave it basis, alone, do not render the agreement an adhesion
contract. Clinic Masters v. District Court, 192 Colo. 120,
556 P.2d 473 (1976). Rather, [t]here must be showing
that the parties were greatly disparate in bargaining power, that
there was no opportunity for negotiation, or that [the] services
could not be obtained elsewhere. Id. In Jones,
the court held that the agreement was not an adhesion contract
and the party seeking exculpation did not possess a decisive bargaining
advantage because the service provided by Free Flight was
not an essential service. Jones, 623 P.2d at 377-78.
788 F. Supp. at 474-475. The court granted defendants
motion for summary judgment. See
also Batterman v. Wells Fargo Ag Credit Corp., 802 P.2d
1112 (Colo. App. 1990), cert.
denied; Jones v. Dressel, 623 P.2d 370 (Colo. 1981); Clinic
Masters v. District Court, 556 P.2d 473 (Colo. 1976).
v. Contract construed against the drafter.
See Public Service Co. of Colorado
v. United Cable Television of Jeffco, 829 P.2d 1280 (Colo. 1992); Stegall
v. Little Johnson Associates, Ltd., 996 F.2d 1043 (10th Cir. 1993); Cheyenne
Mountain School Dist. No. 12 v. Thompson, 861 P.2d 711 (Colo. 1993).
Perhaps the parties can negate this common law rule by an express provision
in the contract.
vi. Failure of essential purpose.
Will the clause in question cause the contract to fail in its essential purpose? See
Cooley v. Big Horn Harvestore Systems, Inc., 813 P.2d 736 (Colo. 1991).
b. Even If The Clauses Are Valid And Enforceable, Do
You Want To Use The Clauses?
The law is reluctant to interfere with the bargaining process, and power, of
the parties to a contract, and does so only in extreme circumstances. The
fact that you may be able to transfer and allocate risks to the other party
to the contract does not mean that you should do it.
(a) Those who impose an unfair contract
upon another party often get what they deserve. For example,
suppose there is a breach of contract. Most jurors, and judges,
can quickly spot an unfair lopsided contract. What will they
do with it, even if they do not say so?
(b) When one party to a contract has been taken advantage of, too
often that fact is reflected in the performance. And then, see
No. l above.
In sum, there is no free ride. Risk management, allocation
and transfer clauses should be used to achieve bargained for conclusions,
to achieve fair results reflecting terms both parties desired, not
terms forced on one party just short of duress or unconscionability. He
who uses the clauses to achieve an unfair or unreasonable allocation
or risks most often will ultimately receive his just desserts.
6. CONCLUSION
The types of risk management allocation and transfer clauses discussed above
are only a few of the many such types of clauses that might be considered. Indeed,
for every risk and every problem in a construction project, there is a contract
clause to eliminate or alleviate the concern.
However, as old-fashioned as it may seem, justice usually will ultimately prevail
to place risks where they properly belong within a broad range. More
important than drafting the clause, is the determination of whether it will
be enforced by the courts, and whether it should be used at all.
|